G3000 Series Installation Instructions

August 11, 2021

Installation Steps

 acrobat download

Model G3000 Installation Instructions

1. A) Position the bottom half of the insulated shield (insulating structural material, sheet metal jacket and load plate) on the pipe at the applicable support location as shown.

2. A) Hold firmly the top half of the shield, open the overlapping sheet metal jacket and gently slide into position the top half of the insulated shield over the bottom half-shield as shown.

3. A) Position the U-Bolt at the appropriate location as shown.
B) Install the nuts and hand tighten until snug tight.

Note:

Provide 1/16″ radial clearance all around between the shield and the U-Bolt except at the bottom as shown in Figure 1.

       

G1000 through G2000 Series Installation Instructions

Installation Steps

 acrobat download

Model G1000 Installation Instructions

1. A) Position the guide straps at the applicable support location as shown.

2. A) Install the bolt through the top ears of the straps and hand tighten nut until snug tight.

Model G2000 Installation Instructions

1. A) Position the guide straps at the applicable support location as shown.

2. A) Install the bolts, nut and spring nut as shown. Hand tighten nut and bolt until snug tight.

3. A) Install the bolts through the top ears of the straps and hand tighten nuts.B) Install the bolts through the top ears of the straps and the spring nuts and hand tighten until snug tight.

       

Note:

Provide 1/16″ radial clearance all around between the shield and the strap except at the bottom as shown in Figure 1 and Figure 2.

E2000 through E2300 Pre-Insulated Riser Clamp Installation Instructions

Installation Steps

 acrobat download

1. A) Position one half of the insulated shield (insulating structural material and sheet metal jacket) on the pipe at the desired location as shown.

2. A) Gently slide the other half of the insulated shield with the     overlapping jacket into position over the previously located     half shield.

3. A) Assemble strap weldments (strap with shop welded outer thrust plates) and line up the bolt holes.

B) Install the bolts, spacers, lock washers and nuts as shown.

C) Hand tighten nuts before applying the specified torque.

D) Select torque value that correspond with the pipe size and model designation of the unit shown on Table 1. During tightening, it is recommended that the nut is turned rather than the bolt head and that the bolts be crosstorqued until the required torque has been achieved to obtain an even pressure on the structural insulation. To ensure that the bolts are properly crosstorqued by checking the spacing (B) between the ears to be approximately the same.

Note:

When models include heat trace groves, the number and location may vary. Check with design drawings for exact number and location. Ensure that the heat tracing cable is properly positioned inside the grove of the shield.

4. A) Locate and position factory supplied inner thrust plates (two on each side of the assembly) on the pipe. See below for locating and positioning the inner thrust plates on the pipe. When properly positioned weld them to the pipe as shown.

Note:

In order to act properly as designed, it is important that there is a zero clearance between the inner thrust plates and structural insert. It is recommended that the inner thrust plates be clamped tight against the structural insert before welding and remained clamped until the weld has completely colled-off to avoid or minimize shrinkage and/or distortion due to welding. If ther eis axial clearance, cut galvanied sheet metal shims to the same outline as the inner thrust plates and isntall them to reduce this clearance to zero.

Inner Thrust Plate Detail

Section A-A

Elevation

Section B-B

       

Notes:
1. Located the inner thrust plates on the side of the assembly directly opposite the outer thrust plates located on the
other side of the unit at all times (see sections A-A and B-B).

2. Position the inner thrust plate to provide equal clearance (*) between the edges of the inner thrust plate and the
two adjacent outer thrust plates as shown above.

* Gap tolerance
– 2 1/2″ thick insulation and less           + 1/8″
– Greater than 2 1/2″ thick insulation    + 1/4″

Table 1
Bolt Torque
Pipe Size E2000 Series E2100 Series E2200 Series E2300 Series
Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
1 3-5 3-5 3-5
1.5 3-5 3-5 5-7
2 3-5 3-5 8-10
2.5 3-5 3-5 8-10
3 3-5 8-10 13-15
3.5 3-5 8-10 13-15
4 3-5 8-10 13-15
5 5-7 13-15 18-20
6 6-8 13-15 23-25
8 8-10 18-20 28-30
10 13-15 28-30 43-45
12 13-15 28-30 43-45 58-60
14 18-20 38-40 58-60 73-75
16 18-20 38-40 58-60 88-90
18 23-25 48-50 73-75 98-100
20 23-25 48-50 73-75 98-100
24 23-25 56-60 88-90 118-120

E1000 through E1300 Pre-Insulated Riser Clamp Installation Instructions

Installation Steps

 acrobat download

1. A) Position one half of the insulated shield (insulating structural material and sheet metal jacket) on the pipe at the desired location as shown.

2. A) Gently slide the other half of the insulated shield with the     overlapping jacket into position over the previously located     half shield.

3. A) Assemble strap weldments (strap with shop welded outer thrust plates) and line up the bolt holes.

B) Install the bolts, spacers, lock washers and nuts as shown.

C) Hand tighten nuts before applying the specified torque.

D) Select torque value that correspond with the pipe size and model designation of the unit shown on Table 1. During tightening, it is recommended that the nut is turned rather than the bolt head and that the bolts be crosstorqued until the required torque has been achieved to obtain an even pressure on the structural insulation. To ensure that the bolts are properly crosstorqued by checking the spacing (B) between the ears to be approximately the same.

Note:

When models include heat trace groves, the number and location may vary. Check with design drawings for exact number and location. Ensure that the heat tracing cable is properly positioned inside the grove of the shield.

4. Locate and position factory supplied inner thrust plates on the pipe. See sheet 3 for locating and positioning the inner thrust plates on the pipe. When properly positioned, weld them to the pipe as shown (see Table 1).

Note:

In order to act properly as designed, it is important that there is a zero clearance between the inner thrust plates and structural insert. It is recommended that the inner thrust plates be clamped tight against the structural insert before welding and remained clamped until the weld has completely colled-off to avoid or minimize shrinkage and/or distortion due to welding. If there is axial clearance, cut galvanized sheet metal shims to the same outline as the inner thrust plates and install them to reduce this clearance to zero.

Inner Thrust Plate Detail

       

Notes:
1. Located the inner thrust plates on the top side of the assembly and offest 90° fromt he location of the outer
plates which are locate dont he other side of the unit.

2. Position the inner thrust plate to provide equal clearance between the edges of the inner thrust plates as shown
above.

* Gap tolerance:
– 2 1/2″ thick insulation and less           + 1/8″
– Greater than 2 1/2″ thick insulation    + 1/4″

Table 1
Bolt Torque
Pipe Size E1000-E10130 E1100-E1130 E1200-E1230 E1300-E1330
Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
3/4 3-5 3-5 3-5
1 3-5 3-5 3-5
1.25 3-5 3-5 5-7
1.5 3-5 3-5 5-7
2 3-5 3-5 8-10
2.5 3-5 3-5 8-10
3 3-5 8-10 13-15
3.5 3-5 8-10 13-15
4 3-5 8-10 13-15
5 5-7 13-15 18-20
6 6-8 13-15 23-25
8 8-10 18-20 28-30
10 13-15 28-30 43-45
12 13-15 28-30 43-45 58-60
14 18-20 38-40 58-60 73-75
16 18-20 38-40 58-60 88-90
18 23-25 48-50 73-75 98-100
20 23-25 48-50 73-75 98-100
24 23-25 56-60 88-90 118-120

D6000 through D6300 Pre-Insulated 2 Rod Hanger Installation Instructions

Installation Steps

 acrobat download

1. Position the bottom half of the insulated hanger shield (insulating structural material and sheet metal jacket) on the pipe at the desired location as shown.

2. A) Gently slide into position the top half of the insulated hanger shield over the bottom half shield as shown.

3. A) Place the straps into position (between the beads) and line up the bolt holes.

B) Install the rods through the strap ears, lock washers, nuts  and hand tighten.

C) Apply torque value on the nuts.

D) Select torque value that correspond with the pipe size and model designation of the unit shown on Table 1. When tightening, it is recommended that the nut is turned rather than the rod and that the rod  be cross torqued until the required torqued has been achieved to obtain an even pressure on the structural insu-lation.

E) To ensure that the bolts are properly cross-torque by checking spacing (B) between the ears shall be approximately the same (see Figure B).

Note: When models include heat trace groves, the number and location may vary. Check with design drawings for exact number and location. Ensure that the heat tracing cable is properly positioned inside the grove of the shield.

Table 1
Bolt Torque
D6000 Series D6100 Series D6200 Series D6300 Series
Pipe Size 3
1″ 3
1 1/2″ 3
2″ 3
2 1/2″ 3
3″ 5
4″ 5
5″ 10 10
6″ 10 10
8″ 10 10
10″ 15 15
12″ 15 15
14″ 15 15
16″ 15 15 30
18″ 15 15 30
20″ 15 15 30 50
24″ 15 15 30 50
26″ 15 15 30 50
30″ 15 15 30 50

D4000 through D5000 Pre-Insulated 2 Rod Hanger Installation Instructions

Installation Steps

 acrobat download

1. A) Position the bottom half of the insulated hanger shield (insulating structural material and sheet metal jacket) on the pipe at the desired location as shown.

D4000-D5000 PAGE 1_3

D4000-D5000 PAGE 1_2

2. A) Gently slide into position the top half of the insulated hanger shield over the bottom half shield as shown.

Note: When models include heat trace groves, the number and location may vary. Check with design drawings for exact number and location. Ensure that the heat tracing cable is properly positioned inside the grove of the shield.

D4000-D5000 PAGE 2_1

3. A) Position straps between the beads.

B) Install the threaded rod (by others), lockwashers and nuts and hand tighten.

C) Apply torque on the bolts.

D) Select torque value that correspond with the pipe size and model designation of the unit shown on Table 1.Below when tightening, it is recommended that the bolts are cross torqued until the required torqued has been achieved to obtain an even pressure on the structural insulation.

E) To ensure that the bolts are properly cross-torqued by checking spacing “B” between the ears shall be approximately the same (see Figure B).

D4000-D5000 PAGE 2_2

Figure B


 

Table 1
Bolt Torque
D4000 Series D5000 Series
Pipe Size Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
1/2″ 1-3 1-3
3/4″ 1-3 1-3
1″ 1-3 1-3
1 1/4″ 1-3 1-3
1 1/2″ 1-3 1-3
2″ 2-4 2-4
2 1/2″ 2-4 2-4
3″ 3-5 3-5
3 1/2″ 3-5 3-5
4″ 3-5 3-5

D1000 through D3300 Pre-Insulated 2 Bolt Hanger Installation Instructions

Installation Steps

 acrobat download

Model D1000-D2000

1. A) Position the bottom half of the insulated hanger shield (insulating structural material and sheet metal jacket) on the pipe at the desired location.

B) Ensure that the bottom half shield is located under the pipe as shown below (Figure A).

Model D3000 – D3300

2. A) Gently slide into position the top half of the insulated hanger shield over the bottom half shield as shown.

3. A) Place the straps into position  (between the beads) and line up the bolt holes.

B) Install the bolts, through the strap ears, spacer, weldless eye nut, lock washers and nuts and hand tighten nuts.

C) Apply torque value on the bolts. Select torque value that correspond with the pipe size and model designation of the unit as shown on  below, (Table 1 for model D1000-D2000, Table 2 for model D3000-D3300)

D) When tightening it is recommended that the nut is turned rather than the bolt head and that the bolts be cross-torqued until the required torque has been achieved to obtain an even pressure on the structural insulation (structural inserts for model D3000-D3300).

E) Ensure that the bolts  are properly cross torqued by checking spacing (B) between the ears  to be approximately the same (see figure B).

Note: When models include heat trace groves, the number and location may vary. Check with design drawings for exact number and location.

 

Table 1
Bolt Torque
D1000 (Series) D2000 (Series) D1000 (Series) D2000 (Series)
Pipe Size Bolt Torque
(FT – LBS)
Bolt Torque
(FT – LBS)
Pipe Size Bolt Torque
(FT – LBS)
Bolt Torque
(FT – LBS)
1/2″ 1-3 1-3 2 1/2″ 2-4 2-4
3/4″ 1-3 1-3 3″ 3-5 3-5
1″ 1-3 1-3 3 1/2″ 3-5 3-5
1 1/4″ 1-3 1-3 4″ 3-5 3-5
1 1/2″ 1-3 1-3 6″ 3-5 3-5
2″ 2-4 2-4

 

Table 2
Bolt Torque
D3000 Series D3100 Series D3200 Series D3300 Series
Pipe Size Bolt Torque
(FT – LBS)
Bolt Torque
(FT – LBS)
Bolt Torque
(FT – LBS)
Bolt Torque
(FT – LBS)
1 1-3 1-3 1-3 1-3
1.5 1-3 1-3 1-3 1-3
2 1-3 1-3 1-3 1-3
2.5 1-3 1-3 1-3 1-3
3 1-3 1-3 1-3 1-3
3.5 1-3 1-3 1-3 1-3
4 1-3 1-3 1-3 1-3
5 8-10 8-10 8-10 8-10
6 8-10 8-10 8-10 8-10
8 8-10 8-10 20-22 20-22
10 13-15 13-15 28-30 28-30
12 13-15 13-15 28-30 28-30
14 13-15 13-15 28-30 28-30
16 13-15 13-15 28-30 28-30
18 13-15 13-15 28-30 28-30
20 13-15 13-15 28-30 48-50
24 13-15 13-15 28-30 48-50
26 13-15 13-15 28-30 48-50
28 13-15 13-15 28-30 48-50
30 13-15 13-15 28-30 48-50
32
36 33-35 42-44
42

C4000 through C4300 Pre-Insulated Positive Pipe Anchor

Installation Steps

 acrobat download

1. A) Center the base weldment assembly (bottom strap with shop welded outer thrust plates) under the applicable support location on the pipe section as shown.

2. A) Insert the lower half shield (structural insulation material and sheet metal jacket) between the outer thrust plates and under the pipe as shown.

3. A) Place the upper half shield (structural insulation material and sheet metal jacket) over the pipe and lower half shield installed in Step 2 as shown.

4. A) Assemble top strap weldment assembly. Top strap with shop welded outer thrust plates over the upper half shield and install the bolts through the clamp ears with nuts on top.

B) Apply the torque on the bolts, select torque value that correspond with the pipe size and model designation of the unit shown on Table 1 below. During tightening, it is recommended that the nut is turned rather than the bolt head and that the bolts be cross-torqued until the required torque has been achieved to obtain an even pressure on the structural insulation.

C) Ensure that the bolts are properly cross-torqued. by checking the spacing “B” between the ears to be approximately the same.

5. A) Locate and position factory supplied inner thrust plates (two on each side of the assembly) on the pipe. Locate and position the inner thrust plates on the pipe. When properly positioned weld them to the pipe shown (see Table 1 for the weld size.)

6. A) Weld base of anchor assembly to support member as shown. Select “W” (Weld Size) that correspond with the pipe size and model designation of the unit. Shown on Table 1.

Note:

In order to act properly as designed, it is important that there is a zero clearance between the inner thrust plates and structural insert. It is recommended that the inner thrust plates be clamped tight against the structural insert before welding and remained clamped until the weld has completely cooled off to avoid or minimize shrinkage and/or distortion due to welding. If theren is axial clearance, cut galvanized sheet metal shims to the same outline as the inner thrust plates and install them to reduce this clearance to zero.

Inner Thrust Plate Detail

Section A-A

Elevation

Section B-B

Section C-C

       

Notes:
1. Located the inner thrust plates on the side of the assembly directly opposite the outer thrust plates located on the other side of the unit at all times (see sections A-A and B-B). DO not install inner thrust plates directly over the outer thrust plates.

2. Position the inner thrust plate to provide equal gap (*) between the edges of the inner thrust plate and the two adjacent outer thrust plates as shown above.

3. Insulator to fill gaps as shown with loose insulation before installing pipe insulation.

Table 1 Bolt Torque & Weld Size (W)
Pipe Size
C4000 Series
C4100 Series
C4200 Series
C4300 Series
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
1″ 5-10 3/16 10-15 3/16 10-15 1/4 10-15 1/4
1.25″ 5-10 3/16 10-15 3/16 10-15 1/4 10-15 1/4
1.5″ 5-10 3/16 10-15 3/16 10-15 1/4 10-15 1/4
2 5-10 3/16 10-15 3/16 10-15 1/4 10-15 1/4
3″ 5-10 3/16 10-15 3/16 10-15 1/4 10-15 1/4
4″ 5-10 3/16 10-15 3/16 10-15 1/4 10-15 1/4
6″ 5-10 3/16 10-15 3/16 20-30 1/4 10-15 1/4
8″ 5-10 3/16 10-15 3/16 20-30 1/4 15-20 1/4
10″ 10-20 1/4 20-30 1/4 20-30 1/4 15-20 1/4
12″ 10-20 1/4 20-30 1/4 20-30 1/4 20-23 1/4
14″ 10-20 1/4 20-30 1/4 20-30 1/4 20-23 1/4
16″ 10-20 1/4 20-30 1/4 30-50 1/4 30-32 5/16
18″ 10-20 1/4 20-30 1/4 30-50 1/4 33-35 5/16
20″ 10-20 1/4 20-30 1/4 30-50 1/4
24″ 10-20 1/4 20-30 1/4 30-50 1/4
26″ 10-20 1/4 20-30 1/4 30-50 1/4
28″ 10-20 1/4 20-30 1/4 30-50 1/4
30″ 30-50 1/4 50-60 1/4 60-75 5/16
36″ 30-50 1/4 50-60 1/4 60-75 5/16
42″ 30-50 1/4 50-60 1/4 60-75 5/16

 

C3000 through C3300 Pre-Insulated Pipe Anchor Installation Instructions


Installation Steps

 acrobat download
C3000-C3300 Installation Instruction_1

1. Position bottom half of the insulated shield into the base assembly. Ensure that the inserts are properly located over the strap by checking that:

A) Each end of shield shall have equal distance (C) from outer edge of strap (Figure A).

B) The 180° section of the bottom half shield shall be parallel to the support base (Figure B).

Slide the base assembly and insulated shield into position under the pipe at the applicable support location.

C3000-C3300 Installation Instruction_2

2. A) Lower the pipe onto the bottom half of the shield.

B) Slide the top shield into position.

C) Gently place the top strap into position above the bottom strap as shown and line up the bolt holes.

C3000-C3300 Installation Instruction_3

3. A) Install the bolts, lockwashers and nuts and hand tighten. For ease of bolt torquing, install the bolts with the nuts on top.

B) Apply torque on the bolts. Select torque value that correspond with the pipe size and model designation of the unit shown on Table 1. When tightening, it is recommended that the nut is turned rather than the bolt head and that the bolts are cross-torqued until the required torque has been achieved to obtain an even pressure on the structural insulation.

C) Ensure that the bolts are properly cross-torqued by checking the spacing “B” between the ears to be approximately the same (see Figure B).

4. When properly positioned, weld base assembly to steel support as shown. Select “W” (weld size) that correspond with the pipe size and model designation of the unit shown Table 1.

       

Table 1

Bolt Torque & Weld Size (W)

Pipe Size
C3000 Series
C3100 Series
C3200 Series
C3300 Series
Bolt Torque
(FT-LBS)
Weld (W) Size Bolt Torque
(FT-LBS)
Weld (W) Size Bolt Torque
(FT-LBS)

Weld (W) Size

Bolt Torque
(FT-LBS)
Weld (W) Size
1″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
1.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
2″ 3-5 3/16″ 3-5 3/16″ 5-7 3/16″ 3-5 3/16″
2.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
3″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
3.5″ 3-5 3/16″ 3-5 3/16″ 8-10 3/16″ 3-5 3/16″
4″ 4-6 3/16″ 7-9 3/16″ 10-12 3/16″ 7-9 3/16″
5″ 4-6 3/16″ 9-11 3/16″ 13-15 3/16″ 9-11 3/16″
6″ 7-9 1/4″ 13-15 1/4″ 20-22 1/4″ 13-15 1/4″
8″ 9-11 1/4″ 18-20 1/4″ 27-29 1/4″ 18-20 1/4″
10″ 10-12 1/4″ 21-23 1/4″ 31-33 1/4″ 21-23 1/4″
12″ 11-13 1/4″ 23-25 1/4″ 34-36 1/4″ 23-25 1/4″
14″ 13-15 1/4″ 26-28 1/4″ 39-41 1/4″ 26-28 1/4″
16″ 18-20 1/4″ 36-38 1/4″ 54-56 1/4″ 36-38 1/4″
18″ 20-22 1/4″ 40-42 1/4″ 60-62 1/4″ 40-42 1/4″
20″ 21-23 1/4″ 43-45 1/4″ 64-66 1/4″ 43-45 1/4″
24″ 23-25 1/4″ 45-47 1/4″ 68-70 1/4″ 45-47 1/4″
26″ 20-25 1/4″ 50-52 1/4″ 75-77 1/4″ 50-52 1/4″
28″ 27-29 1/4″ 54-56 1/4″ 81-83 1/4″ 54-56 1/4″
30″ 39-41 1/4″ 78-80 1/4″ 118-120 1/4″ 78-80 1/4″
32″ 41-43 1/4″ 82-84 1/4″ 123-125 1/4″ 82-84 1/4″
36″ 46-48 1/4″ 92-94 1/4″ *138-140 1/4″ 92-94 1/4″
42″ 52-54 1/4″ 103-105 1/4″ *155-160 1/4″ 103-105 1/4″

* = Requries A-325 Bolt Material

C2000 through C2030 Pre-Insulated Pipe Anchor Installation Instructions


Installation Steps

 acrobat download
c2000-c2030 1

1. Position and slide anchor support between the center line of the pipe and the support member.

2. Weld the anchor support to the support member and to the pipe as shown (see Table 1 below for weld sizes and desired location).

C2000-C2030 Installation Instruction_1

C2000-C2030 Installation Instruction_3
C2000-C2030 Installation Instruction_4


 

Table 1
Pipe Size
C2000 Series
C2010 Series
C2020 Series
C2030 Series
W1 Size
W2 Size
W1 Size
W2 Size
W1 Size
W2 Size
W1 Size
W2 Size
8″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″
10″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″
12″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″
14″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″
16″ 3/16″ 3/16″ 3/16″ 3/16″
18″ 3/16″ 3/16″
20″ 3/16″ 3/16″
24″
26″
28″
30″
36″
42″

C1000 through C1030 Pre-Insulated Welded Pipe Anchor Installation Instructions


Installation Steps

 acrobat download
c1000-c1030 pipe welded anchor 2

1. Position and slide anchor support between the center line of the pipe and the support member.

2. When properly positoned, weld the anchor support to the support member and to the pipe as shown (see Table 1 below).


 

Table 1
Pipe Size
C1000 Series
C1010 Series
C1020 Series
C1030 Series
W1 Size
W2 Size
W1 Size
W2 Size
W1 Size
W2 Size
W1 Size
W2 Size
2″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″
3″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″
4″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″
6″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″ 3/16″
8″ 3/16″ 3/16″ 3/16″ 3/16″
10″ 3/16″ 3/16″ 3/16″ 3/16″
12″ 3/16″ 3/16″ 3/16″ 3/16″
14″ 3/16″ 3/16″
16″ 3/16″ 3/16″
18″
20″
24″
26″
28″
30″
36″
42″

B7000 through B8300 Pre-Insulated Installation Instructions


Installation Steps

 acrobat download
b7000-b8300

1. A) Remove the mounting screw from the slide pad and slide base restraint weldment.

B) Temporarily separate the slide pad from the restraint weldment.

C) Locate and position the restraint weldment on the steel  support to meet the required piping analysis  cold settings (see below for P.S.I. recommended cold settings). Please note that required piping analysis cold settings governs over P.S.I. recommendations.

D) When properly positioned, weld restraint weldment to support steel as shown. Select (W) weld size that correspond with the pipe size and model designation of the unit.

E) Place slide pad on restraint weldment and install  with the mounting screws.

B7000-B7300

Model B7000 – B7300

 

2. Position bottom half of the insulated shield into the base assembly. Ensure that the inserts are properly located over the straps by checking that:

A) Each end of shield shall have equal distance (C) from outer edge of strap (Figure A & A1).

B) The 180° section of the bottom half shield shall be parallel to the support base (Figure B).

b8000-8300 page 2_1

Model: B8000 – B8300 Series

3. A) Slide the base assembly and bottom half shield under the pipe.

A) Each end of shield shall have equal distance (C) from outer edge of strap (Figure A & A1).

B) Position the base assembly on the restraint weldment to allow for anticipated axial travel (see below for P.S.I. recommended axial cold settings).
Note: When models include heat trace groves, the number and location may vary. Check with design drawings for exact number and location. Ensure that the heat tracing cable is properly positioned inside the grove of the shield.

b7000-b8300

Model: B7000 – B7300 Series

4. A) Slide the top half shield into position above the bottom-half shield.

B) Gently place the top strap into position above the bottom strap and line-up the bolt holes.

b8000-b8300

Model: B8000 – B8300 Series

5. A) Install the bolts, lockwashers and nuts and hand tighten. For ease of bolt torquing, install the bolts with the nuts on top.

B) Apply torque on the bolts. Select torque value that corresponds with the pipe size and model designation of the unit shown on table 1 for model B7000-B7300 and table 2 for B8000-B8300. When tightening, It is recommended that the nut is turned rather than the bolt head and that the bolts are cross-torqued until the required torque has been achieved to obtain an even pressure on the structural insulation.

C) Ensure that the bolts are properly cross-torqued by checking the spacing “B” between the ears to be approximately the same (see Figure B).

Note: These units are designed for specific axial travel. Prior to tightening of the bolts, the unit may require cold setting (see figure A & A1 for recommended axial cold setting instructions for this unit).

Completed Assembly
Model B7000 – B7300

        B1000-B2300 PAGE 2_4

Completed Assembly
Model B8000 – B8300

Axial Cold Settings

Position base assembly such that after the support has moved, the center line of the strap (marked by the center line) approximately matches the center line of the restraint weldment (Figure A & A1).

B7000-B8300 PAGE 3_1

Figure A

B7000-B8300 PAGE 3_2

Figure A1

B7000-B8300 PAGE 3_3

Figure B

Table 1
Bolt Torque & Weld Size (W)
Pipe Size B7000 Series B7100 Series B7200 Series B7300 Series
Bolt Torque
(FT – LBS)
Weld (W) Size Bolt Torque
(FT – LBS)
Weld (W) Size Bolt Torque
(FT – LBS)
Weld (W) Size Bolt Torque
(FT – LBS)
Weld (W) Size
1 3-5 3/16 3-5 3/16 3-5 3/16 3-5 3/16
1.5 3-5 3/16 3-5 3/16 3-5 3/16 3-5 3/16
2 3-5 3/16 3-5 3/16 3-5 3/16 3-5 3/16
2.5 3-5 3/16 5-7 3/16 5-7 3/16 3-5 3/16
3 3-5 3/16 7-9 3/16 7-9 3/16 3-5 3/16
3.5 3-5 3/16 8-10 3/16 8-10 3/16 6-8 3/16
4 3-5 3/16 10-12 3/16 10-12 3/16 7-9 3/16
5 3-5 3/16 13-15 3/16 13-15 3/16 9-11 3/16
6 7-9 1/4 20-22 1/4 20-22 1/4 13-15 1/4
8 9-11 1/4 27-29 1/4 27-29 1/4 18-20 1/4
10 10-12 1/4 31-33 1/4 31-33 1/4 21-23 1/4
12 11-13 1/4 34-37 1/4 34-37 1/4 23-25 1/4
14 13-15 1/4 39-41 1/4 39-41 1/4 26-28 1/4
16 18-20 1/4 54-56 1/4 54-56 1/4 36-38 1/4
18 20-22 1/4 60-62 1/4 60-62 1/4 40-42 1/4
20 21-23 1/4 64-66 1/4 64-66 1/4 43-45 1/4
24 23-25 1/4 68-70 1/4 68-70 1/4 45-47 1/4
26 25-27 1/4 75-77 1/4 75-77 1/4 50-52 1/4
28 27-29 1/4 81-83 1/4 81-83 1/4 54-56 1/4
30 39-41 1/4 118-120 1/4 118-120 1/4 78-80 1/4
32 41-43 1/4 123-125 1/4 123-125 1/4 82-84 1/4
36 46-48 1/4 *138-140 1/4 *135-140 1/4 92-84 1/4
42 52-54 1/4 *155-157 1/4 *155-157 1/4 103-105 1/4
* Requires A325 Bolt Material

 

Table 2
Bolt Torque & Weld Size (W)
Pipe Size B8000 Series B8100 Series B8200 Series B8300 Series
Bolt Torque
(FT – LBS)
Weld (W) Size Bolt Torque
(FT – LBS)
Weld (W) Size Bolt Torque
(FT – LBS)
Weld (W) Size Bolt Torque
(FT – LBS)
Weld (W) Size
1 3-5 3/16 3-5 3/16 3-5 3/16 3-5 3/16
1.5 3-5 3/16 3-5 3/16 3-5 3/16 3-5 3/16
2 3-5 3/16 3-5 3/16 3-5 3/16 3-5 3/16
2.5 3-5 3/16 3-5 3/16 3-5 3/16 3-5 3/16
3 3-5 3/16 3-5 3/16 3-5 3/16 3-5 3/16
3.5 3-5 3/16 3-5 3/16 3-5 3/16 3-5 3/16
4 3-5 3/16 3-5 3/16 5-7 3/16 3-5 3/16
5 3-5 3/16 3-5 3/16 7-9 3/16 3-5 3/16
6 3-5 1/4 7-9 1/4 10-12 1/4 7-9 1/4
8 3-5 1/4 9-11 1/4 13-15 1/4 9-11 1/4
10 5-7 1/4 10-12 1/4 16-18 1/4 10-12 1/4
12 6-8 1/4 12-14 1/4 17-19 1/4 12-14 1/4
14 7-9 1/4 13-15 1/4 20-22 1/4 13-15 1/4
16 9-11 1/4 18-20 1/4 27-29 1/4 18-20 1/4
18 10-12 1/4 20-22 1/4 30-32 1/4 20-22 1/4
20 11-13 1/4 21-23 1/4 32-34 1/4 21-23 1/4
24 11-13 1/4 23-25 1/4 34-36 1/4 23-25 1/4
26 13-15 1/4 25-27 1/4 38-40 1/4 25-27 1/4
28 13-15 1/4 27-29 1/4 40-42 1/4 27-29 1/4
30 20-22 1/4 39-41 1/4 59-61 1/4 39-41 1/4
32 20-22 1/4 41-43 1/4 61-63 1/4 41-43 1/4
36 23-25 1/4 46-48 1/4 68-70 1/4 46-48 1/4
42 26-28 1/4 52-54 1/4 77-79 1/4 51-53 1/4

B5000 through B6300 Pre-Insulated Installation Instructions


Installation Steps

 acrobat download
B5000-B6300 Series

1. A) Remove the mounting screw from the slide pads and mounting plates.

B) Temporarily separate the slide pad from the mounting plate.

C) Locate and position the mounting plate on the steel support to meet the required piping analysis cold settings (see below, for P.S.I. recommended cold settings). Please note that  required piping analysis cold settings governs over P.S.I. recommendations).

D) When properly positioned, weld mounting plate to support steel as shown. Select “w” (weld size) that correspond with the pipe size and model designation of the unit.

E) Place slide pad on mounting plate and install with the mounting screw.

Model: B5000 – B5300

 

2. Position bottom half of the insulated shield into the base assembly. Ensure that the inserts are properly located over the strap by checking that:

A) Each end of shield shall have equal distance (c) from outer edge of strap (Figure A & A1).

B) The 180° section of the bottom half shield shall be parallel to the support base (Figure B).

Model B6000 – B6300

3. A) Slide the base assembly and bottom half shield under the pipe.
B) position the base assembly on the mounting plate to allow for anticipated axial and lateral travel (see below for p.s.i. recommended axial and lateral cold settings).

Notes:
When models include heat trace groves, the number and location may vary. Check with design drawings for exact number and location. Ensure that the heat tracing cable is properly positioned inside the grove of the shield.

B5000-B6300 PAGE 2_1

Model: B5000-B5300

4. A) Slide the top half shield into position above the bottom-half shield.

B) Gently place the top strap into position above the bottom strap and line-up the bolt holes.

B5000-B6300 PAGE 2_2

Model: B6000-B6300

5. A) Install the bolts, lockwashers and nuts and hand tighten. For ease of bolt torquing, install the bolts with the nuts on top.

B) Apply torque on the bolts. Select torque value that corresponds with the pipe size and model designation of the unit shown on table 1 for model B3000-B3300 and table 2 for B4000-B4300. When tightening, it is recommended that the nut is turned rather than the bolt head and that the bolts are cross-torqued until the required torque has been achieved to obtain an even pressure on the structural insulation.

C) Ensure that the bolts are properly cross-torqued by checking the spacing “B” between the ears to be approximately the same (see Figure B).

Note:

These units are designed for specific axial travel. Prior to tightening of the bolts, the unit may require cold setting (see figure A & A1 for recommended axial cold setting instructions for this unit).

B5000-B6300 PAGE 2_2

Completed Assembly
Model: B5000-B5300

        B5000-B6300 PAGE 2_4

Completed Assembly
Model: B6000-B6300

Axial & Lateral Cold Settings

A) Axial cold setting: Position base assembly such that after the support has moved, the center line of the strap (marked by the center line) approximately matches the center line of the slide pad (Figure A & A1).

B5000-B6300 PAGE 3_1

B5000-B6300 PAGE 3_2

B) Lateral cold setting: For lateral cold setting, match the center of the base assembly over the center of the slide pad assembly (Figure B).

 

Table 1

Bolt Torque & Weld Size (W)

Pipe Size
B5000 Series
B5100 Series
B5200 Series
B5300 Series
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
1″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
1.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
2″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
2.5″ 3-5 3/16″ 3-5 3/16″ 5-7 3/16″ 3-5 3/16″
3″ 3-5 3/16″ 3-5 3/16″ 7-9 3/16″ 3-5 3/16″
3.5″ 3-5 3/16″ 6-8 3/16″ 8-10 3/16″ 6-8 3/16″
4″ 3-5 3/16″ 7-9 3/16″ 10-12 3/16″ 7-9 3/16″
5″ 3-5 3/16″ 9-11 3/16″ 13-15 3/16″ 9-11 3/16″
6″ 7-9 1/4″ 13-15 1/4″ 20-22 1/4″ 13-15 1/4″
8″ 9-11 1/4″ 18-20 1/4″ 27-29 1/4″ 18-20 1/4″
10″ 10-12 1/4″ 21-23 1/4″ 31-33 1/4″ 21-23 1/4″
12″ 11-13 1/4″ 23-25 1/4″ 34-37 1/4″ 23-25 1/4″
14″ 13-15 1/4″ 26-28 1/4″ 39-41 1/4″ 26-28 1/4″
16″ 18-20 1/4″ 36-38 1/4″ 54-56 1/4″ 36-38 1/4″
18″ 20-22 1/4″ 40-42 1/4″ 60-62 1/4″ 40-42 1/4″
20″ 21-23 1/4″ 43-45 1/4″ 64-66 1/4″ 43-45 1/4″
24″ 23-25 1/4″ 45-47 1/4″ 68-70 1/4″ 45-47 1/4″
26″ 25-27 1/4″ 50-52 1/4″ 75-77 1/4″ 50-52 1/4″
28″ 27-29 1/4″ 54-56 1/4″ 81-83 1/4″ 54-56 1/4″
30″ 39-41 1/4″ 78-80 1/4″ 118-120 1/4″ 78-80 1/4″
32″ 41-43 1/4″ 82-84 1/4″ 123-125 1/4″ 82-84 1/4″
36″ 46-48 1/4″ 92-94 1/4″ *138-140 1/4″ 92-94 1/4″
42″ 52-54 1/4″ 103-105 1/4″ *155-157 1/4″ 103-105 1/4″

* = Requries A-325 Bolt Material

 

Table 2 Bolt Torque & Weld Size (W)
Pipe Size
B6000 Series
B6100 Series
B6200 Series
B6300 Series
Bolt Torque
(FT-LBS
)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
1″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
1.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
2″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
2.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
3″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
3.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
4″ 3-5 3/16″ 3-5 3/16″ 5-7 3/16″ 3-5 3/16″
5″ 3-5 3/16″ 3-5 3/16″ 6-8 3/16″ 3-5 3/16″
6″ 3-5 1/4″ 7-9 1/4″ 10-12 1/4″ 7-9 1/4″
8″ 3-5 1/4″ 9-11 1/4″ 13-15 1/4″ 9-11 1/4″
10″ 5-7 1/4″ 10-12 1/4″ 16-18 1/4″ 10-12 1/4″
12″ 6-8 1/4″ 11-13 1/4″ 17-19 1/4″ 11-13 1/4″
14″ 7-9 1/4″ 13-15 1/4″ 20-22 1/4″ 13-15 1/4″
16″ 9-11 1/4″ 18-20 1/4″ 27-29 1/4″ 18-20 1/4″
18″ 10-12 1/4″ 20-22 1/4″ 30-32 1/4″ 20-22 1/4″
20″ 11-13 1/4″ 21-23 1/4″ 32-34 1/4″ 21-23 1/4″
24″ 11-13 1/4″ 23-25 1/4″ 34-36 1/4″ 23-25 1/4″
26″ 13-15 1/4″ 25-27 1/4″ 38-40 1/4″ 25-27 1/4″
28″ 13-15 1/4″ 27-29 1/4″ 40-42 1/4″ 27-29 1/4″
30″ 20-23 1/4″ 39-41 1/4″ 59-61 1/4″ 39-41 1/4″
32″ 20-23 1/4″ 41-43 1/4″ 61-63 1/4″ 41-43 1/4″
36″ 23-25 1/4″ 46-48 1/4″ 69-71 1/4″ 46-48 1/4″
42″ 26-28 1/4″ 52-54 1/4″ 78-80 1/4″ 52-54 1/4″

 

B3000 through B4300 Pre-Insulated Support Installation Instructions


Installation Steps

 acrobat download
B3300-B4300

1. A) Remove the mounting screw from the slide pad and slide base restraint weldment.

B) Temporarily separate the slide pad from the restraint weldment.

C) Locate and position the restraint weldment on the steel  support to meet the required piping analysis  cold settings (see below for P.S.I. recommended cold settings). Please note that required piping analysis cold settings governs over P.S.I. recommendations.

D) When properly positioned, weld restraint weldment to support steel as shown. Select (W) weld size that correspond with the pipe size and model designation of the unit.

E) Place slide pad on restraint weldment and install  with the mounting screws.

B3000-B3300

Model: B3000 – B3300

 

2. Position bottom half of the insulated shield into the base assembly. Ensure that the inserts are properly located over the strap(s) by checking that:

A) Each end of shield shall have equal distance (c) from outer edge of strap (Figure A or A1).

B) The 180° section of the bottom half shield shall be parallel to the support base (Figure 8).

B4000-B4300

Model: B4000-B4300

3. A) Slide the base assembly and bottom half shield under the pipe.
(B) Position the base assembly on the restraint weldment to allow for anticipated axial travel.

Notes:
When models include heat trace groves, the number and location may vary. Check with design drawings for exact number and location. Ensure that the heat tracing cable is properly positioned inside the grove of the shield.

B3000-B3300

Model: B3000 – B3300

4. A) Slide the top half shield into position above the bottom-half shield.

B) Gently place the top strap into position above the bottom strap and line-up the bolt holes.

B4000-B4300

Model: B4000-B4300

5. A) Install the bolts, lockwashers and nuts and hand tighten. For ease of bolt torquing, install the bolts with the nuts on top.

B) Apply torque on the bolts. Select torque value that corresponds with the pipe size and model designation of the unit shown on table 1 for model B3000-B3300 and table 2 for B4000-B4300. When tightening, it is recommended that the nut is turned rather than the bolt head and that the bolts are cross-torqued until the required torque has been achieved to obtain an even pressure on the structural insulation.

C) Ensure that the bolts are properly cross-torqued by checking the spacing “B” between the ears to be approximately the same (see Figure B).

Note:

These units are designed for specific axial travel. Prior to tightening of the bolts, the unit may require cold setting (see figure A & A1 for recommended axial cold setting instructions for this unit).

B3000-B4300 Completed Assembly 1

Completed Assembly
Model: B3000 – B3300

        B3000-B4300 Completed Assembly 2

Completed Assembly
Model: B4000-B4300

Axial Cold Settings

A) Position base assembly such that after the support has moved, the center line of the strap (marked by the center line) approximately matches the center line of the restraint weldment (Figure A & A1).

B3000-B4300 PAGE 3_1

Figure A

B3000-B4300 PAGE 3_2

Figure A1

B3000-B4300 PAGE 3_3

Figure B

 

Table 1Bolt Torque & Weld Size (W)
Pipe Size
B3000 Series
B3100 Series
B3200 Series
B3300 Series
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
1″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
1.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
2″ 3-5 3/16″ 3-5 3/16″ 5-7 3/16″ 3-5 3/16″
2.5″ 3-5 3/16″ 3-5 3/16″ 6-8 3/16″ 3-5 3/16″
3″ 3-5 3/16″ 5-7 3/16″ 7-9 3/16″ 3-5 3/16″
3.5″ 3-5 3/16″ 6-8 3/16″ 8-10 3/16″ 6-8 3/16″
4″ 3-5 3/16″ 7-9 3/16″ 11-13 3/16″ 7-9 3/16″
5″ 3-5 3/16″ 9-11 3/16″ 13-15 3/16″ 9-11 3/16″
6″ 7-9 1/4″ 14-16 1/4″ 20-22 1/4″ 14-16 1/4″
8″ 9-11 1/4″ 18-20 1/4″ 27-29 1/4″ 18-20 1/4″
10″ 11-13 1/4″ 21-23 1/4″ 32-34 1/4″ 21-23 1/4″
12″ 12-14 1/4″ 23-25 1/4″ 35-37 1/4″ 23-25 1/4″
14″ 13-15 1/4″ 27-29 1/4″ 40-42 1/4″ 27-29 1/4″
16″ 18-20 1/4″ 37-39 1/4″ 55-57 1/4″ 37-39 1/4″
18″ 20-22 1/4″ 41-43 1/4″ 61-63 1/4″ 41-43 1/4″
20″ 22-24 1/4″ 43-45 1/4″ 65-67 1/4″ 43-45 1/4″
24″ 23-25 1/4″ 46-48 1/4″ 69-71 1/4″ 46-48 1/4″
26″ 25-27 1/4″ 51-53 1/4″ 76-78 1/4″ 51-53 1/4″
28″ 27-29 1/4″ 55-57 1/4″ 82-84 1/4″ 55-57 1/4″
30″ 40-42 1/4″ 80-82 1/4″ 120-122 1/4″ 80-82 1/4″
32″ 42-44 1/4″ 85-87 1/4″ *127-129 1/4″ 85-87 1/4″
36″ 47-49 1/4″ 93-95 1/4″ *140-142 1/4″ 93-95 1/4″
42″ 53-55 1/4″ 105-107 1/4″ *158-160 1/4″ 105-107 1/4″
48″ 60-62 1/4″ 120-122 1/4″ *180-185 1/4″ 120-122 1/4″

* = Requries A-325 Bolt Material

Table 2Bolt Torque & Weld Size (W)
Pipe Size
B4000 Series
B4100 Series
B4200 Series
B4300 Series
Bolt Torque
(FT-LBS
)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
Bolt Torque
(FT-LBS)
Weld (W) Size
1″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
1.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
2″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
2.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
3″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
3.5″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″ 3-5 3/16″
4″ 3-5 3/16″ 3-5 3/16″ 5-7 3/16″ 3-5 3/16″
5″ 3-5 3/16″ 3-5 3/16″ 7-9 3/16″ 3-5 3/16″
6″ 3-5 1/4″ 7-9 1/4″ 10-12 1/4″ 7-9 1/4″
8″ 5-7 1/4″ 9-11 1/4″ 14-16 1/4″ 9-11 1/4″
10″ 5-7 1/4″ 11-13 1/4″ 16-18 1/4″ 11-13 1/4″
12″ 6-8 1/4″ 12-14 1/4″ 18-20 1/4″ 12-14 1/4″
14″ 7-9 1/4″ 13-15 1/4″ 20-22 1/4″ 13-15 1/4″
16″ 9-11 1/4″ 18-20 1/4″ 28-30 1/4″ 18-20 1/4″
18″ 10-12 1/4″ 20-22 1/4″ 31-33 1/4″ 20-22 1/4″
20″ 11-13 1/4″ 22-24 1/4″ 33-35 1/4″ 22-24 1/4″
24″ 11-13 1/4″ 23-25 1/4″ 34-36 1/4″ 23-25 1/4″
26″ 13-15 1/4″ 25-27 1/4″ 38-40 1/4″ 25-27 1/4″
28″ 14-16 1/4″ 27-29 1/4″ 41-43 1/4″ 27-29 1/4″
30″ 20-22 1/4″ 40-42 1/4″ 60-62 1/4″ 40-42 1/4″
32″ 21-23 1/4″ 42-44 1/4″ 62-64 1/4″ 42-44 1/4″
36″ 23-25 1/4″ 47-49 1/4″ 70-72 1/4″ 47-49 1/4″
42″ 26-28 1/4″ 53-55 1/4″ 79-81 1/4″ 53-55 1/4″

A1000 through A9000 Insulated Support Installation Instructions


Installation Steps

 acrobat download
a1000-a4000-a9000

Model A1000 – A4000 & A9000

1. Position the bottom half of the insulated hanger shield (insulating structural material, sheet metal jacket and load plate where applicable) on the pipe at the applicable support location as shown.

2. Hold the top half of the shield firmly. Open the overlapping sheet metal jacket and gently slide into position the top half of the insulated shield over the bottom half shield as shown.

a5000-a8400

Model A5000 – A8400

1. When used on a flat surface, position shield so that it is centered on the structural steel.

2. When used with a clevis hanger, position shield symmetrically.

3. When models include heat trace groves, the number and location may vary. Check with design drawings for exact number and location. Ensure that the heat tracing cable is properly positioned inside the grove of the shield.

Completed assembly without load plate

Completed Assembly Without Load Plate

completed assembly with load plate

Completed Assembly With Load Plate

Top