Installation Steps

  1. A) position one half of the insulated shield(insulating structural material and sheet metal jacket) on the pipe at the desired location as shown.



2. A) Gently slide the other half of the insulated shield with the overlapping jacket into position over the previously located half shield.

3. A) Assemble strap weldments (strap with shop welded outer thrust plates) and line up the bolt holes.

B Install the bolts, spacers, lock washers and  nuts as shown.

C) Hand tighten nuts before applying the specified torque.

D) Select torque value that corres- pond with the pipe size and model designation of the unit as shown on table 1. During tightening, it is recommended that the nut is turned rather than the bolt head and  that the bolts be cross-torqued until the required torque has been achieved to obtain an even pressure on the structural insulation. To ensure that the bolts are properly crosstorqued by checking the spacing (b) between  the ears to be approximately the same.

4. A) Locate and position factory supplied inner thrust plates (two on each side of the assembly) on the pipe. See below for locating and positioning the inner thrust plates on the pipe. When properly positioned weld them to the pipe as shown.

Note:

In order to act properly as designed, it is important that there is a zero clearance between the inner thrust plates and structural insert. It is recommended that the inner thrust plates be clamped tight against the structural insert before welding and remained clamped until the weld has completely colled-off to avoid or minimize shrinkage and/or distortion due to welding. If ther eis axial clearance, cut galvanied sheet metal shims to the same outline as the inner thrust plates and isntall them to reduce this clearance to zero.

 

Inner Thrust Plate Detail

Section A-A Elevation Section B-B
  1. Located the inner thrust plates on the side of the assembly directly opposite the outer thrust plates located on the
    other side of the unit at all times (see sections A-A and B-B).
  2. Position the inner thrust plate to provide equal clearance (*) between the edges of the inner thrust plate and the
    two adjacent outer thrust plates as shown above.

* Gap tolerance
- 2 1/2" thick insulation and less           + 1/8"
- Greater than 2 1/2" thick insulation    + 1/4"

Table 1
Bolt Torque
Pipe Size E2000 Series E2100 Series E2200 Series E2300 Series
Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
Bolt Torque
(FT-LBS)
1 3-5 3-5 3-5  
1.5 3-5 3-5 5-7  
2 3-5 3-5 8-10  
2.5 3-5 3-5 8-10  
3 3-5 8-10 13-15  
3.5 3-5 8-10 13-15  
4 3-5 8-10 13-15  
5 5-7 13-15 18-20  
6 6-8 13-15 23-25  
8 8-10 18-20 28-30  
10 13-15 28-30 43-45  
12 13-15 28-30 43-45 58-60
14 18-20 38-40 58-60 73-75
16 18-20 38-40 58-60 88-90
18 23-25 48-50 73-75 98-100
20 23-25 48-50 73-75 98-100
24 23-25 56-60 88-90 118-120
 

 

 

Parent Company: Piping Technology: Pipe Supports, Pipe Clamps, & Pipe Hardware
Fellow Subsidiaries
U.S. Bellows: Metallic & Fabric Expansion Joints, Bellows
Sweco Fab: ASME Vessels, Pig Launchers, Spectacle Blinds

Pipe Shields: Pre-Insulated Pipe Supports, Slides, Guides & Anchors
Fronek Anchor/Darling
: Snubbers, Sway Struts & Sway Braces
Contact Us: 707-447-5014 Toll Free1-800-538-7007. info@pipeshields.com

Copyright 2017 Pipe Shields, Inc. All Rights Reserved. Contact Us | Privacy Policy